Reference
Construction Terms
A plain-language glossary of the abbreviations and terms you'll encounter on this site and on real job sites.
50 of 50 terms
- Allowance
- A placeholder dollar amount included in a bid for items not yet selected (e.g., tile, fixtures). Actual cost may be higher or lower.
- American Institute of ArchitectsAIA
- Publisher of the most widely used standard contract forms in U.S. construction (e.g., AIA A101, A201).
- Architect / EngineerA/E
- The design professionals responsible for the drawings and specifications. Often a single team for smaller projects.
- Architectural, Structural, MEPArch / Struct / MEP
- The three primary disciplines on most drawing sets.
- As-Builts
- Drawings updated at project close-out to reflect what was actually built, including any field changes.
- Bid
- A contractor's priced proposal to perform a defined scope of work, usually based on plans and specifications.
- Bid Leveling
- Comparing competing bids line by line to ensure each contractor priced the same scope, so an apples-to-apples comparison is possible.
- Building Information ModelingBIM
- A 3D digital model of the building used for coordination, clash detection, and quantity takeoffs.
- By Others
- Work shown for reference but performed by a different party — flag these early to avoid scope gaps.
- Certificate of OccupancyCO / C of O
- A document from the local building authority certifying that the structure complies with codes and is safe to occupy.
- Change OrderCO
- A written modification to the original contract that adjusts scope, price, or schedule. Should be signed before the work proceeds.
- Construction DocumentsCDs
- The final, permit-ready set of drawings and specifications that contractors bid and build from.
- Contingency
- Money set aside in the budget to cover unforeseen conditions or changes during construction. Typically 5–15% of hard costs.
- Cost-Plus
- Owner reimburses actual costs plus an agreed fee or percentage. Transparent but uncapped without a GMP.
- Critical Path
- The sequence of dependent tasks that determines the shortest possible project duration. Delays on the critical path delay the whole job.
- Dry-In
- The point at which the building envelope is weather-tight (roof, wrap, windows) and interior work can proceed.
- Final Completion
- All punch list items closed, final paperwork delivered, and the contract fully performed.
- Finish Work
- The visible, final-stage trades — trim carpentry, paint, tile, flooring, cabinetry, fixtures.
- General ContractorGC
- The company that contracts to build the project — hires subs, schedules trades, pulls permits, and stands behind the workmanship.
- Guaranteed Maximum PriceGMP
- A contract type where the contractor agrees that costs won't exceed a stated cap; savings below the cap may be shared.
- Hard Costs
- Direct construction costs — labor, materials, equipment — for the physical building.
- Heating, Ventilation, Air ConditioningHVAC
- The systems that condition indoor air for comfort and air quality.
- Lien Waiver
- A signed document from a contractor or supplier waiving their right to file a mechanic's lien for work already paid for.
- Linear FootLF
- Unit of length used for pricing trim, framing lumber, and similar run-based items.
- Lump Sum
- A fixed-price contract for a defined scope. Risk of overrun shifts to the contractor.
- Mechanical, Electrical, PlumbingMEP
- The building systems that make a structure habitable — HVAC, power and lighting, water and waste.
- Not In ContractNIC
- Items shown on drawings or discussed but explicitly excluded from the contractor's scope.
- Notice to ProceedNTP
- Written authorization from the owner directing the contractor to start work on a defined date.
- Occupational Safety and Health AdministrationOSHA
- Federal agency that sets and enforces workplace safety standards, including for construction sites.
- On CenterOC
- The spacing between repeating elements measured center-to-center (e.g., studs at 16" OC).
- Owner-Furnished, Contractor-InstalledOFCI
- Items the owner buys directly but the contractor installs (e.g., appliances). Important to flag in the contract.
- Owner's RepresentativeOR / Owner's Rep
- An independent construction professional hired by the project owner to oversee, advise, and advocate on their behalf throughout the project.
- Pay ApplicationPay App
- The contractor's monthly invoice showing percent-complete by line item and the amount due that period.
- Personal Protective EquipmentPPE
- Hard hats, safety glasses, gloves, hi-vis vests, and similar gear required on most active job sites.
- Plans & Specs
- Shorthand for the drawings (plans) and the written specifications that together define the work.
- Punch List
- A list of small, often cosmetic items that must be completed or corrected by the contractor before the project is considered final.
- Request for InformationRFI
- A written question from a contractor to the design team asking for clarification on drawings, specs, or field conditions.
- Request for ProposalRFP
- A formal document soliciting bids from contractors, defining the scope, schedule, and submission requirements for a project.
- Retainage
- A percentage (often 5–10%) of each pay application withheld by the owner until the project is substantially complete.
- Rough-In
- The stage when MEP systems are run inside walls and floors before insulation and drywall close them up.
- Schedule of ValuesSOV
- A breakdown of the contract sum into line items used to track progress and process pay applications.
- Scope of WorkSOW
- The written description of exactly what work is — and is not — included in a contract.
- Shop Drawings
- Detailed fabrication drawings prepared by a sub or supplier showing how an item will actually be built and installed.
- Soft Costs
- Project costs not directly tied to construction — design fees, permits, insurance, financing, owner's rep fees.
- Square FootSF / sq ft
- Standard unit of area used for pricing, takeoffs, and reporting (e.g., $/SF).
- SubcontractorSub
- A specialty trade contractor hired by the GC to perform a defined scope of work (framing, electrical, plumbing, etc.).
- Submittal
- Product data, samples, and shop drawings the contractor sends to the design team for review before installation.
- Substantial Completion
- The point at which the project is sufficiently complete for the owner to occupy or use it for its intended purpose.
- Time and MaterialsT&M
- A pricing method where the owner pays actual labor hours plus material cost plus a markup. Common for unknown-scope work.
- Walk-Through
- A scheduled site visit where the owner, contractor, and (often) owner's rep review work in place — typically used for progress reviews, pre-drywall inspections, and final punch list creation.
